D3. SCOPE OF WORK
D3.1 The Work to be done under the Contract shall consist of three parts:
(a) Part 1 – Federal Government Funded Work
(b) Part 2 – Manitoba Hydro Funded Work
(c) Part 3 – City Funded Work
Part 1 – Federal Government Funded Work
D3.2
Part 1 – Federal Government Funded Work shall consist of:
(a) Structural Soil Cells and Related Forestry Work
(i) South side of Broadway from Osborne Street to Main Street
Part 2 – Manitoba Hydro Funded Work
D3.3
Part 2 – Manitoba Hydro Funded Work shall consist of:
(a) Street Lighting and Associated Works
(i) South side of Broadway from Osborne Street to Main Street
Part 3 – City Funded Work
D3.4 Part 3 – City Funded Work shall consist of:
(a) Pavement Rehabilitation
(i) Eastbound Broadway from Osborne Street to Main Street
(b) Water and Waste Work
(i) Broadway (MH70055014) - Manhole Repair
(ii) Broadway (MH20012944) - Manhole Repair
(iii) Broadway (MH70038689) – Manhole Repair
(iv) Broadway (MH20012770) – Manhole Repair
(v) Broadway (MH70051680) – Manhole Repair
(vi) Broadway (MH70051679) – Manhole Repair
(vii) Broadway (MH20012792) – Manhole Repair
(viii) Broadway (MH70054996) – Abandon Manhole
(ix) Broadway (MH70054995) – Abandon Manhole
(x) Broadway (MH70054993) – Abandon Manhole
(xi) Broadway (MH70054992) – Abandon Manhole
(xii) Broadway (MH70054994) – Abandon Manhole
(xiii) Broadway (MH1) – Manhole Inspection
(xiv) Broadway (MA70114137) – Sewer Inspection
(c) Traffic Signals Work – North and South side of Broadway
(i) Traffic Signals – Broadway and Osborne Street
(ii) Traffic Signals – Broadway and Memorial Boulevard
(iii) Traffic Signals – Broadway and Kennedy Street
(iv) Traffic Signals – Broadway and Edmonton Street
(v) Traffic Signals – Broadway and Carlton Street
(vi) Traffic Signals – Broadway and Hargrave Street
(vii) Traffic Signals – Broadway and Donald Street
(viii) Traffic Signals – Broadway and Smith Street
(ix) Traffic Signals – Broadway and Garry Street
(x) Traffic Signals – Broadway and Fort Street
(xi) Traffic Signals – Broadway and Main Street
D3.5 The City currently has no approved funding in the Capital Budget for Part 1 of the
Work. Part 1 of the Work is contingent upon the Federal Government approving sufficient funding.
D3.5.1 Further to C7.1, if notice of sufficient funding is not received, the City shall
have the right to eliminate all or any portion of Part 1, and the Contract Price will be reduced
accordingly.
D3.5.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to
D3.5.1 shall not be considered in calculating the aggregate reduction in the Contract Price for
purposes of C7.5.
D3.5.3 If all or any portion of Part 1 is eliminated pursuant to D3.5.1, the time
periods stipulated in D25 for Substantial Performance of the Work and in D26 for Total Performance
of the Work will be reduced proportionally by the Contract Administrator acting reasonably.
D3.6 The City currently has no approved funding in the Capital Budget for Part 2 of the
Work, but is anticipating receiving notification about funding from Manitoba Hydro during the Award
Period. Part 2 of the Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.6.1 Further to C7.1, if notice of sufficient funding is not received, the City shall
have the right to eliminate all or any portion of Part 2, and the Contract Price will be reduced
accordingly.
D3.6.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to
D3.6.1 shall not be considered in calculating the aggregate reduction in the Contract Price for
purposes of C7.5.
D3.6.3 If all or any portion of Part 2 is eliminated pursuant to D3.6.1, the time
periods stipulated in D25 for Substantial Performance of the Work and in D26 for Total Performance
of the Work will be reduced proportionally by the Contract Administrator acting reasonably.
D3.7 The major components of the Work are as follows:
(a) Pavement Rehabilitation
(i) Installation of Traffic Signals infrastructure
(ii) Complete manhole and sewer Work (sewer inspections as required)
(iii) Planing existing asphalt pavement
(iv) Full depth concrete repairs of existing joints and slabs
(v) Connection to existing sewer
(vi) Connection to existing manholes and existing services
(vii) Replacement of existing catch basins and catch basin leads
(viii) Adjustment of catch basins, sewer manholes, appurtenances, and utility manholes
(ix) Removal of existing sidewalk
(x) Installation of street light bases, conduit, new light standards and street light cable
(xi) Insulation of water services (as required)
(xii) Installation of Structural Soil Cells including catchbasins, subdrain, distribution pipe,
transfer pipe, three Manitoba Hydro conduits and all other related items
(xiii) Connection and Installation of conduit and cabling for Winnipeg Transit Heated Shelters
(xiv) Renewal of existing curbs
(xv) Installation of detectable warning tiles
(xvi) Construct new 175 mm reinforced concrete sidewalk c/w paving stone band
(xvii) Construction of concrete Winnipeg Transit shelter bases and power pedestal bases
(xviii) Placement of asphalt overlay (Type 1A, average thickness 85 mm)
(xix) Supply and placement of paving stones
(xx) Installation of Downtown Biz amenities (bike racks and street furniture)
(xxi) Boulevard restoration