D3. SCOPE OF WORK
D3.1 The Work to be done under the Contract shall consist of two parts:
(a) Part 1 – City Funded Work
(b) Part 2 – Manitoba Hydro Funded Work.
Part 1 – City Funded Work
D3.2 Part 1 – City Funded Work shall consist of:
(a) Concrete Reconstruction
(i) Sargent Avenue from St. James Street to Empress Street.
Part 2 – Manitoba Hydro Funded Work
D3.3 Part 2 – Manitoba Hydro Funded Work shall consist of:
(a) Street Lighting and Associated Works
(i) Sargent Avenue from St. James Street to Empress Street.
D3.4 The City currently has no approved funding in the Capital Budget for Part 2 of the Work, but is
anticipating receiving notification about funding from Manitoba Hydro by late May 2021. Part 2
of the Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.4.1 Further to C7.1, if notice of sufficient funding is not received, the City shall have the right to
eliminate all or any portion of Part 2, and the Contract Price will be reduced accordingly.
D3.4.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to D3.4.1
shall not be considered in calculating the aggregate reduction in the Contract Price for
purposes of C7.5.
D3.4.3 If all or any portion of Part 2 is eliminated pursuant to D3.4.1, the time periods stipulated in
D19 for Substantial Performance of the Work and in D20 for Total Performance of the
Work will be reduced proportionally by the Contract Administrator acting reasonably.
D3.5 The major components of the Work are as follows:
(a) Concrete Reconstruction
(i) Removal of existing pavement and sidewalk;
(ii) Milling asphalt overlay;
(iii) Installation of catch basins, sewer service pipe and subdrains;
(iv) Insulation of water services;
(v) Compaction of sub-grade;
(vi) Placement of separation/ filtration geotextile fabric and Class A geogrid;