Construction of landscape and surface works generally consisting of:
• 400 lm of storm installation
• 11,000 cm of amended topsoil placement
• 37,000 sm of irrigation installation
• 38,000 sm of sod installation
• 12 soccer goal post installation
• 1,800 lm of chain link fence installation
• 4 backstop installations
• 13,000 sm of shale installation
• 20 sand horseshoe pits installations
• 100 sm of concrete runners installation
• 300 lm of post on post barrier installation
• 1,500 sm of onsite topsoil placement
• 63,000 sm of seed installation
• 9,000 cm of onsite topsoil relocation
• 5,000 sm of gravel pathway installation
• 6 portable bleacher installations
• 2 portable soccer shelter installations
• 8 concrete dugout constructions
• 400 sm of asphalt spectator pad installation
• 1 batting cage installation
• 1 overhead structure installation
• 260 sm of concrete pad installation
Optional Work:
• 1 prefabricated washroom installation
• 9,500 sm of parking asphalt placement
• 900 lm of concrete pin curb installation
• 1,100 sm of onsite topsoil placement
• 150 tree plantings
• 1,200 shrub plantings
• 1,500 sm of mulch installation
• 9,500 sm of asphalt pathways placement
• 175 lm of parking lot lighting conduit
• 2 parking lot lighting fixtures
• 300 sm of rubber playground surfacing