For the purpose of this contract, the Contractor will be responsible for supplying all emulsion and all aggregate for all contract sections.
As outlined in the Special Provisions, the contractor will be responsible for all construction aspects of the single chip seal operations.
Section I – Vicinity of McGregor
Application of Single Chip Seal and Fog Seal on Provincial Trunk Highway 1 (West Bound) from Provincial Trunk Highway 34 to 1.0km West of Provincial Trunk Highway 16, for a total construction distance approximately 36.4 kms in the Municipality of Langford.
Section II - Vicinity of Ashern
Application of Single Chip Seal and Fog Seal on Provincial Trunk Highway 6 from North Junction of Provincial Trunk Highway 68 to South Jct of Provincial Road 325, for a total construction distance of approximately 26.0 kms in the Municipality of Grahamdale.
Section III - Vicinity of Rapid City
Application of Single Chip Seal and Fog Seal on Provincial Trunk Highway 10 from 0.4km North of Provincial Trunk Highway 25 to 4.5km North of Provincial Trunk Highway 24, for a total construction distance of approximately 15.7 kms in the Municipality of Saskatchewan.
Section IV - Vicinity of Westbourne
Application of Single Chip Seal and Fog Seal on Provincial Trunk Highway 16 from Provincial Trunk Highway 50 to 3.8km North of Provincial Trunk Highway 1, for a total construction distance of approximately 24.1 kms in the Municipality of Westbourne.
Section V - Vicinity of Neepawa
Application of Single Chip Seal and Fog Seal on Provincial Trunk Highway 16 from the East Junction of Provincial Trunk Highway 5 to Provincial Trunk Highway 34, for a total construction distance of approximately 36.4 kms in the Municipality of Langford.