Segment 1 - PTH 1 (Portage Ave) to PR 221
Location 1 – West Service Road (3.30km North of PTH 1)
Work involves building embankment, crushed rock, granular base course and drainage improvements 600m south of Boychuk road to Provincial Trunk Highway 190 for a total construction distance of approximately 800m in the Municipality of Rosser.
Location 2 – PTH 101 (2.7km North of PTH 190)
The work involves removing direct access from Road 63N onto Provincial Trunk Highway 101 (i.e., east and west accesses) c/w median opening removal including removing pavement, earth excavation, removing metal culverts and removing and installing concrete curbing in the Municipality of Rosser.
Location 3 – PR 221 (PTH 101 Interchange)
The work involves extension of the existing westbound bypass lane, including crushed rock, granular base course and bituminous pavement c/w regrading of the west service road connection at Provincial Road 221 in the Municipality of Rosser.
Segment 2 – PTH 101 (PR 221 to PTH 7)
Location 4 – PTH 101 North Service Road (PR 236 to Lilyfield)
The work involves reconstruction and construction of an embankment, including horizontal road realignment, widening/benching, surface preparation, granular base course, bituminous pavement, drainage improvements c/w installation of metal pipes, in the Municipality of Rosser.
Location 5 – PTH 101 (2.6km East of PTH 6)
The work involves removing the direct access (north) from Sturgeon Road onto Provincial Trunk Highway 101, including removing metal culverts, removing pavement, acceleration and deceleration lanes and landscaping in the Municipality of Rosser.
Segment 3 – PTH 101 (Highway 7 to Pipeline Rd.)
Location 6 –Holmes Road (King Edward St. Intersection)
The work involves realignment of the King Edward intersection, removing existing metal pipes, installation of metal pipes, excavation, bench cut, ditching and gravelling in the Municipality of Rosser.
Location 7– Holmes Road (King Edward St. to Ritchie Street)
The work involves raising the vertical alignment (i.e.., centreline road profile), removing and installing metal pipes, excavation, bench cutting, ditching and gravelling for a total construction distance of approximately 1.4 km in the Municipality of Rosser.
Segment 4 - PTH 101 (Pipeline to Highway 8)
Location 8– Holmes Road (Pipeline to Second Street)
The work involves surface preparation type, base and bituminous pavement including, granular base course, from Pipeline Road to Second Street, for a total construction distance of approximately 2.9km, in the Municipality of West St. Paul.
Location 9– Kapelus Road Repair various locations
The work involves construction of embankment, including roadway excavation, granular base course and bituminous pavement, for a total construction distance of approximately 0.2km, in the Municipality of West St. Paul.
Location 10 – PTH 101 (PTH 15 and Franklin Ave Access/Apron)
The work involves surface preparation, granular base course and bituminous pavement at PTH 15 and Franklin Ave Access/Apron, in the Municipality of Springfield.