DESCRIPTION OF THE WORK
The Work shall consist in all that is required for the supply and delivery DDP of six (6) under rotor
maintenance platforms for Pine Falls Generating Station manufactured all in accordance with the
Purchaser's drawings, consisting of but not limited to, the following ITEMS:
ITEM 1 - Supply of platform for Unit 4
ITEM 2 - Supply of platform for Unit 3
ITEM 3 - Supply of platform for Unit 1
ITEM 4 - Supply of platform for Unit 2
ITEM 5 - Supply of platform for Unit 5
ITEM 6 - Supply of platform for Unit 6
Descriptions of ITEMS and the Work above are provided as a general overview. Refer to the balance
of the Request for Quotation and Contract for additional information concerning ITEMS and the Work.
WORK SCHEDULE
The Purchaser expects to award a Purchase Order on or about October 25, 2017 and that the
Work will proceed according to the following schedule:
DESCRIPTION DELIVERY DATE
ITEM 1 December 15, 2017
ITEM 2 January 15, 2018
ITEM 3 February 15, 2018
ITEM 4 March 15, 2018
ITEM 5 April 15, 2018
ITEM 6 May 15, 2018
In carrying out the Work, the Contractor shall have reasonable latitude to organize the sequence of the
Work, provided that the various stages of the Work are completed by the specified date(s) or the
date(s) proposed by the Contractor and accepted by the Purchaser.