Full Title: Professional Consulting Services for 2022-2025 Regional Street Renewal Program - Leila Avenue, Partridge Avenue and McGregor Street
D4. SCOPE OF SERVICES
D4.1 The project consists of Regional Street Renewals on Leila Avenue, McGregor Street, and
Partridge Avenue, as well as an active transportation facility along Leila Avenue.
(a) In general, the scope of the project is to execute the Regional Street renewal project
locations in D3.3, with in the annual cash flow limitations in D3.3
(b) For planning and bidding purpose, planned treatment, project budget, assumed working days for
construction are provided below and scoping in Appendix B – Project Locations
nical Scoping;
D4.2 The Services required under this Contract are identified below:
(a) Preliminary Design Services as outlined in D5;
(b) Detailed Design Services (including Tender Preparation) as outlined in D6;
(i) design and specification development;
(ii) drawing preparation;
(iii) procurement process.
(c) Contract Administration Services as outline in D7;
(d) Post-Construction Services as outlined in D8.
D4.2.1 The Services required shall be in accordance with the City’s Project Management
Manual http://winnipeg.ca/infrastructure/asset-management-program/templates-manuals.stm#2 and
templates http://winnipeg.ca/infrastructure/asset-management-program/templates- manuals.stm#4 .
Notwithstanding the foregoing, the Consultant is being engaged by the City for its professional
expertise; the Consultant shall bring to the Consulting Contract Administrator’s attention any
aspect of the City’s Project Management Manual or templates which the Consultant is of the opinion
is not consistent with good industry practice.
D4.3 Further to D4.2(a) the Consultant is expected to complete the Preliminary Design
including:
(a) Class 3 estimate;
(b) Preliminary scheduling and staging plans, minimizing impacts to the travelling public and
local businesses, schools, and residents.
D4.4 Further to D4.2, following Preliminary Design, Detailed Design will proceed as per the
established schedule, approved by the Consulting Contract Administrator.
D4.5 As part of the Preliminary design phase the Consultant is expected to prepare staging
plans that coordinate with other projects in the area. The projects known in the area but not
limited to are:
(a) Water and Waste work projects, including the Armstrong Combined Sewer Relief Project along
Leila, 2023-2025;
(b) Public Works multi-year Capital project on Inkster Boulevard and McGregor Street pital
project (RFP No. 547-2023)
(c) Local Streets projects adjacent to McGregor Street, Partridge Avenue, and Leila Avenue.
D4.6 The Services required under this Contract shall consist of:
(a) Rehabilitation of Leila Avenue from McPhillips Street to McGregor Street and the additional
of an Active Transportation path from the Hydro Right-of-Way west of McPhillips to Diplomat Ave in
accordance with the specifications in D4.1.
(b) Renewal of McGregor Street and Partridge Avenue in accordance with the specifications in
D4.1.
D4.7 For the purposes of bidding, it can be assumed that the project will require a minimum
of two (2) construction contracts.
D4.8 The Project Locations and Technical Scope is subject to final approval of the
Consulting Contract Administrator.
(a) Substitutions and/or deletions that may occur within the consulting assignment and may result
in an adjustment in Fees as per B8.3, Work already completed for work identified in the consulting
assignment prior to the notification of adjustment in the consulting assignment will be paid at
hourly rates identified in the proposal for the actual time completed prior to notification. There
will be no financial compensation if there is a reduction in the consulting assignment.
D4.9 Within the Project phases in D4, the Consultant may be required – depending upon
location and technical scope of services – to conduct site investigation services, materials
testing services, geotechnical services, Underground Structures acquisitions, pipeline loading
assessments, ground-penetrating radar inspections, and/or closed circuit television (CCTV) sewer
inspection and sewer assessment.
D4.9.1 Notwithstanding C8, Fees for Subconsultants engaged to perform services in D4.8
shall be payable as invoiced by the Subconsultant, plus an allowed handling fee of 5%.
D4.9.2 Consultant Fees for supervision of Subconsultants required to perform any
services in D4.8 shall be included in the Consultant’s fees.
D4.10 Further to D4.1, and without limitation to the detailed scope of services outlined
throughout D4, it is expected that key issues will include (but are not limited to):
(a) Traffic management (section D5.6 and D6.3(n));
(b) Coordination with utilities;
(c) Coordination with Water and Waste to renew watermain on Redwood Avenue between Charles
Street and Main Street;
(d) Coordinating with individual fronting businesses and residences, in advance of and during
construction;
(e) Coordination required with Traffic Signals for the adjustment and renewal of the pedestrian
corridors and traffic signals as required through out the project. Investigate tree trimming a
pedestrian crossing to improve sight lines;
(f) Coordination required with Transportation Division for geometric improvements;
(g) Coordination with Transit Department, specifically to consolidate and upgrade Transit stops
to reflect Transits long term planning;
(h) Public information preparation/coordination during construction;
(i) Identification and coordination as applicable with proximal capital project, development
projects, events, festivals.
D4.11 The Consultant will coordinate their activities with (including but not limited to):
(a) City of Winnipeg (various departments and branches), including but not limited to Public
Works Engineering, Parks and Open Spaces, Traffic Signals, Traffic Services, Traffic Management,
Street Lighting, Underground Structures, Streets Maintenance,
Transit Department, Planning Property & Development
Department, Real Estate, Urban Design, Insurance, Legal Services, and Materials
Management;
(b) The Water and Waste Department and/or their representative(s), for the renewal or abandonment
of the water mains, for the televising and renewal or abandonment of the sewer mains, water and
sewer repairs, as well as insulating water services for Concrete Reconstructions;
(c) Public information preparation/coordination during construction;
(d) Identify and coordinate as applicable with development projects, events, festivals;
(e) Coordinating with individual fronting businesses and residences, in advance of and during
construction;
(f) Coordinate access with schools and daycares within the project limits, construction should
occur while school is not in session;
(g) The Winnipeg Parking Authority;
(h) Winnipeg Transit regarding the impact of the Project on their operations and bus stops;
(i) Any and all Utilities or agencies having infrastructure in the Project area, or that may be
impacted by the Project;
(j) City of Winnipeg Forestry Branch and the Consulting Contract Administrator for review of
tree protection, removals and plantings for all locations.
D4.12 Where applicable, the following shall apply to the Services:
(a) City of Winnipeg’s Accessibility Design Standards (2015) and Universal Design Policy at:
www.winnipeg.ca/ppd/Universal_Design.stm;
(b) the most current edition of The City of Winnipeg Standard Construction Specifications City of
Winnipeg Standard Construction Specifications;
(c) City of Winnipeg’s Project Management Manual, also at LINK;
(d) City of Winnipeg’s Tree Planting Details and Specifications Downtown Area and Regional
Streets, also at http://winnipeg.ca/publicworks/parksOpenSpace/UrbanForestry/default.stm;
(e) City of Winnipeg’s Tree Removal Guidelines, also at
http://winnipeg.ca/publicworks/parksOpenSpace/UrbanForestry/default.stm;
(f) City of Winnipeg’s 2012 Draft Updated Transportation Standards Manual (previous version
February 1991);
(g) Manual for the Production of Construction Drawings – City of Winnipeg (November 1984);
(h) Winnipeg Pedestrian and Cycling Strategies (adopted July 15, 2015) Winnipeg Pedestrian and
Cycling Strategies;
(i) The most recent version of the Manual of Temporary Traffic Control on City Streets, at:
https://legacy.winnipeg.ca/publicworks/trafficControl/manual-temporary-traffic-control.stm
(j) Appropriate geometric standards set by the Transportation Association of Canada (TAC);
(k) Current and best practices in pedestrian and cycling infrastructure design;
(l) Street Renewal Definitions
https://www.winnipeg.ca/publicworks/construction/roadway/roadRenewalDefinitions.stm#u ndefined
D4.13 The following documents are to be considered, where applicable:
(a) OurWinnipeg (adopted July 20, 2011);
https://legacy.winnipeg.ca/interhom/cityhall/ourwinnipeg/default.stm
(b) OurWinnipeg Sustainable Transportation Strategy (adopted July 20, 2011);
https://legacy.winnipeg.ca/interhom/cityhall/ourwinnipeg/default.stm
(c) Winnipeg Transportation Master Plan (adopted November 16, 2011).
https://winnipeg.ca/publicworks/transportation/transportationmasterplan.stm
D4.14 Unless otherwise specified below, Appendix A – Definition of Professional Consultant
Services
– Engineering – Public Works shall be applicable to the provision of Professional Engineering
services for this Project.
D4.15 The Consultant will be responsible for project reporting and support to the City’s
Consulting Contract Administrator for project reporting in accordance with the City of Winnipeg’s
Project Management Manual and templates at http://winnipeg.ca/infrastructure/asset-management-
program/templates-manuals.stm#2.
D4.16 The funds available for this Contract are $1,100,000.00