D3.1 The Work to be done under the Contract shall consist of three parts:
(a) Part 1 – City Funded Work
(b) Part 2 – Provincially Funded Work.
(c) Part 3 – Manitoba Hydro Funded Work
Part 1 – Confirmed Provincially Funded Work
D3.2 Part 1 – Confirmed Provincially Funded Work shall consist of:
(a) Riverbank Stabilization Works
(i) Construction of temporary access ramp(s) and working platform;
(ii) Drilling of rockfill column shafts;
(iii) Supply, placement and compaction of rockfill for rockfill columns
(iv) Excavation of rockfill ribs
(v) Supply, placement and compaction of rockfill for rockfill ribs;
(vi) Removal of temporary access ramp(s) and reshaping of riverbank;
Part 2 –Work Contingent on Provincial Funding
D3.3 Part 2 – Provincially Funded Work shall consist of:
(a) Riverbank Grading
(i) Pathway Embankment Construction
(ii) Riverbank Grading
(iii) Supply and Placement of topsoil (planting medium)
(iv) Supply and Installation of Erosion Control Blanket
(b) Road and Pathway Works
(i) Removal of existing asphalt pavement and curbs.
(ii) Barrier curb and gutter renewal (150 mm curb height).
(iii) Placement of base course material on roadway
(iv) Placement of asphalt pavement for roadway (Type 1A, 100 mm thick (2 lifts))
(v) Placement of separation/ filtration geotextile fabric, subbase material, Class B geogrid and base course for pathway.
(vi) Adjustment of existing manhole frame and covers
(vii) Placement of asphalt pavement for pathway (Type 1A, 75 mm thick (1 lift)).
(c) Large Caliper Tree Plantings
Part 3 –Work Contingent on Manitoba Hydro Funding
D3.4 Part 3 – Manitoba Hydro Funded Work shall consist of:
(a) Streetlighting and Associated Works
(i) Installation of temporary overhead feeds
(ii) Removal of existing street lighting poles
(iii) Installation of concrete bases
(iv) Installation of new street lighting cables (trenching and/or boring) and poles (including connections)
D3.5 The City currently has no approved funding in the Capital Budget for Part 2 of the Work, but is anticipating receiving notification about funding from the Province of Manitoba by late December 2020. Part 2 of the Work is contingent upon the Province approving sufficient funding.
D3.5.1 Further to C7.1, if notice of sufficient Provincial funding is not received, the City shall have the right to eliminate all or any portion of Part 2, and the Contract Price will be reduced accordingly.
D3.5.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to D3.5.1 shall not be considered in calculating the aggregate reduction in the Contract Price for purposes of C7.5.
D3.5.3 If all or any portion of Part 2 is eliminated pursuant to D3.5.1, the time periods stipulated in D20 for Substantial Performance of the Work and in D21 for Total Performance of the Work will be reduced proportionally by the Contract Administrator acting reasonably.
D3.6 The City currently has no approved funding in the Capital Budget for Part 3 of the Work, but is anticipating receiving notification about funding from Manitoba Hydro by late December 2020. Part 3 of the Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.6.1 Further to C7.1, if notice of sufficient Manitoba Hydro funding is not received, the City shall have the right to eliminate all or any portion of Part 3, and the Contract Price will be reduced accordingly.
D3.6.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to D3.6.1 shall not be considered in calculating the aggregate reduction in the Contract Price for purposes of C7.5.
D3.6.3 If all or any portion of Part 3 is eliminated pursuant to D3.6.1, the time periods stipulated in D20 for Substantial Performance of the Work and in D21 for Total Performance of the Work will be reduced proportionally by the Contract Administrator acting reasonably.