Full Title: Professional Consulting Services for the Pembina Highway Bridge Deck Rehabilitation Over La Salle River
D4. SCOPE OF SERVICES
D4.1 The Services required under this Contract shall consist of Professional Consulting
Services in accordance with the following:
(a) Deck Investigation and Bearing Inspection as outlined in D5.
(b) Detailed Design of the rehabilitation needed for both structures as outlined in D6.
(c) Contract Administration Services as outlined in D7
(d) Post Construction Services as outlined in D8
D4.1.1 The Services required under D4.1 shall be in accordance with the City’s Project
Management Manual http://winnipeg.ca/infrastructure/asset-management-
program/templates-manuals.stm#2 and templates http://winnipeg.ca/infrastructure/asset-
management-program/templates-manuals.stm#4 . Notwithstanding the foregoing, the Consultant is being
engaged by the City for its professional expertise; the Consultant shall bring to the City’s
attention any aspect of the City’s Project Management Manual or templates which the Consultant is
of the opinion is not consistent with good industry practice.
D4.1.2 The successful proponent will coordinate their activities with (including but
not limited to):
(a) City of Winnipeg (various departments and branches), including but not limited to Public
Works: Engineering, Traffic Signals, Traffic Services, Traffic Management, Transportation Planning,
Parks; Transit Department, Legal Services, Materials Management, and Corporate Communications.
D4.2 City’s proposed project schedule for the work is:
(a) Deck investigation Phase to commence September/October 2023.
(b) Detailed Design Phase to commence in January 2024.
(c) Tendering in April 2024.
(d) Rehabilitation of the first structure in summer 2024 and the second structure in summer 2025.
D4.3 The funds available for this Contract are $250,000.00, including Type 2 Disbursements.