D3. SCOPE OF WORK
D3.1 The Work to be done under the Contract shall consist of:
(a) Minor Rehabilitation
(i) Jewett Bay from Sinnott Street to Sinnott Street.
(b) Major Rehabilitation
(i) Carpathia Road from Corydon Avenue to 360 metres south of Corydon Avenue.
(ii) Renfrew Street from Grant Avenue to Taylor Avenue.
(iii) Campbell Street from Mathers Avenue to Taylor Avenue.
(c) Alley Reconstruction (Asphalt Pavement)
(i) Hudson Street West Alley from Clarence Avenue to Waller Avenue.
(d) Reconstruction (Concrete Pavement)
(i) Carpathia Road from Kenaston Boulevard to 100 metres East of Kenaston
Boulevard.
(e) Asphalt Rehabilitation
(i) Linton Lane from Wexford Street to Swann Drive.
(ii) Biscayne Bay from McGillivray Place to McGillivray Place.
(f) Asphalt Resurface
(i) Ascot Bay from Laxdal Road to Laxdal Road.
(ii) Brock Street from Corydon Avenue to Grosvenor Avenue.
(g) Sewer Repairs and Associated Works
(i) Jewett Bay from Sinnott Street to Sinnott Street.
(ii) Linton Lane from Wexford Street to Swann Drive.
(iii) Carpathia Road from Kenaston Boulevard to 100 metres East of Kenaston
Boulevard.
(iv) Carpathia Road from Corydon Avenue to 360 metres south of Corydon Avenue.
(v) Renfrew Street from Grant Avenue to Taylor Avenue.
(vi) Campbell Street from Mathers Avenue to Taylor Avenue.
(vii) Brock Street from Corydon Avenue to Grosvenor Avenue.
(viii) Biscayne Bay from McGillivray Place to McGillivray Place.
(ix) Hudson Street West Alley from Clarence Avenue to Waller Avenue.
D3.2 The major components of the Work are as follows:
(a) Minor Rehabilitation
(i) Planing of existing lip curbs;
(ii) Construction of concrete joint repairs;
(iii) Construction of modified lip curb (slip form);
(iv) External sewer point repairs;
(v) Slab replacement;
(vi) Concrete Joint Repairs;
(vii) Placement of pavement repair fabric;
(viii) Adjusting catch basin and manhole frame and covers;
(ix) Adjustment of drainage inlets;
(x) Construction of asphalt overlay (40-80mm of Type 1A);
(xi) Boulevard regrading;
(xii) Placement of topsoil; and
(xiii) Placement of sod.
(b) Major Rehabilitation
(i) Milling of existing asphalt overlay, where applicable;
(ii) External sewer point repairs;
(iii) Slab replacement;
(iv) Installation of geogrid fabrics over underlying granular materials;
(v) Concrete Joint Repairs;
(vi) Placement of pavement repair fabric;
(vii) Replacement of curb inlets with curb & gutter catch pits or catch basins;
(viii) Adjusting catch basin and manhole frame and covers;
(ix) Sidewalk renewal;
(x) Installation of detectable tile;
(xi) Select curb renewals;
(xii) Construction of asphalt overlay (40-80mm of Type 1A;
(xiii) Placement of topsoil; and
(xiv) Placement of sod or seed.
(c) Alley Reconstruction (Asphalt Pavement)
(i) Removal of existing pavement within project limits;
(ii) Installation of new catch pits, catch basins, and manholes;
(iii) Connection to existing LDS sewer;
(iv) Installation of subdrains and land drainage sewer;
(v) External sewer point repairs;
(vi) Replacement of curb inlets with curb & gutter catch pits or catch basins;
(vii) Excavation;
(viii) Subgrade compaction;
(ix) Installation of geotextile and geogrid fabrics;
(x) Construction of granular base course and sub-base;
(xi) Construction of reinforced concrete alley approach;
(xii) Construction of concrete catch basin and manhole isolations;
(xiii) Construction of asphalt pavement (50mm of Type 1A, 75mm of Type III);
(xiv) Sidewalk renewal;
(xv) Construction of concrete curbs and curb and gutter;
(xvi) Construction of new private approach tie-ins;
(xvii) Construction of lip curb;
(xviii) Placement of imported fill;
(xix) Boulevard regrading;
(xx) Placement of topsoil; and
(xxi) Placement of sod or seed.
(d) Reconstruction (Concrete Pavement)
(i) Removal of existing pavement within designated area;
(ii) Installation of new catch basins and catch pits.
(iii) Installation of subdrains and land drainage sewer;
(iv) External sewer point repairs;
(v) Removal of roots from sewer;
(vi) Excavation;
(vii) Installation of geogrid fabrics over underlying granular materials;
(viii) Construction of granular base course;
(ix) Adjusting catch basin and manhole frame and covers;
(x) Construction of mainline concrete pavement (150 reinforced);
(xi) Construction of integral barrier curbs;
(xii) Construction of reinforced concrete approaches;
(xiii) Renewal of sidewalks;
(xiv) Installation of imported fill for backfill within the removal of road widening;
(xv) Regrading of boulevards;
(xvi) Placement of topsoil; and
(xvii) Placement of sod or seed.
(e) Asphalt Rehabilitation
(i) Milling of existing asphalt pavement;
(ii) Preparation of existing granular base course;
(iii) Installation of granular base course;
(iv) Catch basin and manhole adjustments;
(v) Renewal of curbs, curb and gutter, and lip curbs;
(vi) Culvert replacement;
(vii) Adjusting catch basin and manhole frame and covers;
(viii) Construction of mainline asphalt pavement (50-80mm of Type 1A);
(ix) Renewal of asphalt approach;
(x) Construction of concrete approaches and isolations;
(xi) Adjustment/repair of private approach tie-ins;
(xii) Placement of topsoil; and
(xiii) Placement of sod or seed.
(f) Asphalt Resurface
(i) Milling/removal of existing asphalt pavement (50-80mm);
(ii) Prepare existing granular base to restore drainage;
(iii) Installation of granular base course to restore crossfall;
(iv) Installation of geogrid fabrics over underlying granular materials;
(v) Adjusting catch basin and manhole frame and covers;
(vi) Curb renewals;
(vii) Construction of mainline asphalt pavement (50-80mm of Type 1A);
(viii) Construction of concrete approaches and isolations, where indicated;
(ix) Construction of private approach tie ins, where indicated;
(x) Placement of topsoil; and
(xi) Placement of sod or seed.
(g) Sewer Repairs and Associated Works
(i) External point repairs of existing sewers;
(ii) Removal of Roots;
(iii) Sewer and sewer service video inspection.