D3.1 The Work to be done under the Contract shall consist of:
(a) Regional Sidewalk Renewals
(i) Higgins Avenue (North Side), Annabella Street to Mordaunt Street
(ii) Osborne Street (West Side), Rathgar Avenue to Hethrington Avenue
(iii) Sutherland Avenue (North Side), Main Street to Argyle Street N
(b) Local Sidewalk Renewals
(i) Barratt Avenue (Both Sides), Spruce Street to Clifton Street
(ii) Bruce Avenue (South Side), Moray Street to Ainslie Street
(iii) Bruce Avenue (North Side), Ainslie Street to Rita Street
(iv) Chudley Street (West Side), Manitoba Avenue to Tyndall Avenue
(v) Laurel Bay (North Side), Hillhouse Road to Diplomat Drive
(vi) Sherburn Street (Both Sides), Ellice Avenue to St. Matthews Avenue
(c) New Local Sidewalk Construction
(i) Beecher Avenue (South Side), Swailes Avenue to Ferrier Street
D3.2 The major components of the Work are as follows:
(a) Regional Sidewalk Renewals
(i) Sidewalk Removal;
(ii) Curb Removal;
(iii) Monolithic Curb and Concrete Sidewalk Removal;
(iv) Supply and Placement of Base Course;
(v) Adjustment of Catch Basins/Manholes;
(vi) Adjustment of Valve Boxes;
(vii) Adjustment of Curb Stops;
(viii) Construct 100mm Monolithic Curb and Concrete Sidewalk with Block-outs for
Paving Stones;
(ix) 100 mm Concrete Sidewalk Renewal;
(x) Curb Renewal;
(xi) Supply and Installation of MMA Markings;
(xii) 100mm Monolithic Curb and Concrete Sidewalk Construction;
(xiii) Installation of Detectable Warning Surface Tiles;
(xiv) Construction of Asphalt Patches;
(xv) Installation of Interlocking Paving Stone;
(xvi) Grading of Boulevard; and
(xvii) Sodding.
(b) Local Sidewalk Renewals
(i) 100mm Concrete Sidewalk Removal;
(ii) 150mm Concrete Sidewalk Removal;
(iii) Curb Renewal;
(iv) Supply and Placement of Base Course;
(v) Adjustment of Catch Basins/Manholes;
(vi) Adjustment of Valve Boxes;
(vii) Adjustment of Curb Stops;
(viii) 100mm Concrete Sidewalk Construction;
(ix) 150mm Reinforced Concrete Sidewalk Construction;
(x) Construction of Asphalt Patches;
(xi) Grading of Boulevard; and
(xii) Sodding.
(c) New Local Sidewalk
(i) Tree Removal;
(ii) Excavation;
(iii) Sub-Grade Compaction;
(iv) Supply and Placement of Base Course;
(v) Curb Renewal;
(vi) 100mm Concrete Sidewalk Renewal;
(vii) 150mm Concrete Sidewalk Renewal;
(viii) Construct 100mm Concrete Sidewalk;
(ix) Grading of Boulevard; and
(x) Sodding.