Part 1 – City Funded Work
D3.2 Part 1 – City Funded Work shall consist of:
(a) Asphalt Reconstruction and Associated Work
(i) Wall Street from St. Matthews Avenue to Notre Dame Avenue
Part 2 – Manitoba Hydro Funded Work
D3.3 Part 2 – Manitoba Hydro Funded Work shall consist of:
(a) Street Lighting and Associated Work
(i) Wall Street from St. Matthews Avenue to Notre Dame Avenue
D3.4 The City currently has no approved funding in the Capital Budget for Part 2 of the Work, but is
anticipating receiving notification about funding from Manitoba Hydro prior to Award. Part 2 of
the Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.4.1 Further to C7.1, if notice of sufficient funding is not received, the City shall have the right to
eliminate all or any portion of Part 2, and the Contract Price will be reduced accordingly.
D3.4.2 Further to C7.5, C7.5.1, and C7.6, a reduction in the Contract Price pursuant to D3.4.1
shall not be considered in calculating the aggregate reduction in the Contract Price for
purposes of C7.5.
D3.4.3 If all or any portion of Part 2 is eliminated pursuant to D3.4.1, the time periods stipulated in
D18.1 for Substantial Performance of the Work and in D21 for Total Performance of the
Work will be reduced proportionally by the Contract Administrator acting reasonably.
D3.5 The major components of the Work are as follows:
(a) Asphalt Reconstruction and Associated Work
(i) Removal of Existing Pavement;
(ii) Excavation;
(iii) External Point Sewer and Manhole Repairs;
(iv) Installation of catch basins and sewer service pipe;
(v) Watermain Service Insulation;
(vi) Compaction of sub-grade;