B3. SITE INVESTIGATION
B3.1 The Consulting Contract Administrator or an authorized representative will conduct a
Site investigation tour of the Winnipeg Drinking Water Treatment Plant (WTP) on May 1, 2024
starting at 1:00 pm.
B3.2 Proponents are required to register for the Site investigation by contacting the
Consulting Contract Administrator identified in D2 a minimum of 24 hours prior to the Site
investigation.
B3.2.1 Proponents registered for a Site investigation must provide the Consulting
Contract Administrator with a Global Sanctions and Politically Exposed Persons (PEP) check obtained
not earlier than one (1) year prior to the Site investigation
(a) The Global Sanctions & PEP Check must be obtained from Sterling Talent Solutions. Proponents
will need to setup a Sterling Talent Solutions account prior to requesting individual background
checks. This process should be done a minimum of 72 hours prior to requesting the first check. The
account can be setup using the following link:
http://forms.sterlingbackcheck.com/partners/platform2-en.php?&partner=winnipegcity
Note that the check will take up to 48 hours to complete. Refer to E1.1.1 of PART E - Security
Clearance for further information.
(b) The results of the Global Sanctions & PEP Check must be received by the City directly through
Sterling Talent Solutions. Proponents must set up an account with Sterling Talent Solutions
directly under their company name and grant Sterling Talent Solutions permission to share the
results of the Global Sanctions & PEP Checks with the City.
B3.2.2 Attendees are required to wear CSA approved footwear, hardhat, and safety vest
while inside the WTP.
B3.2.3 The City will not be providing access to the interior of any drinking water
treatment process channels or tanks during the Site investigation.
B3.3 Although attendance at the Site Investigation is not mandatory, the City strongly
suggests that Proponents attend to view the general Site conditions and limitations of the Work.